Resolution Number 04-09 Ordering Plans
RESOLUTION NUMBER 04-09
RECEIVING FEASIBILITY REPORT AND ORDERING IMPROVEMENT AND PREPARATION OF PLANS
WHEREAS, pursuant to Resolution of the City Council adopted May 5, 2008, a report has been prepared by Benchmark Engineering with reference to proposed Improvement No. MI08-4, the improvement of entire length of Agate Street by replacement of storm sewer, and this report was received by the City Council on February 2, 2009, and
WHEREAS, the report provides information regarding whether the proposed improvement is necessary, cost-effective, and feasible; whether it should best be made as proposed or in connection with some other improvement; and the estimated cost of the improvement as recommended.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF MOUNTIAN IRON, MINNESOTA:
1. Such improvement is necessary, cost-effective, and feasible as detailed in the feasibility report.
2. Such improvement is hereby ordered as proposed in the City Council Resolution adopted 5th day of May 2008.
3. Such improvement has no relationship to the comprehensive municipal plan.
4. Benchmark Engineering is hereby designated as the engineer for this improvement. The engineer shall prepare plans and specifications for the making of such improvement.
DULY ADOPTED BY THE CITY COUNCIL THIS 2nd DAY OF FEBRUARY, 2009.
____________________________________
Mayor Gary Skalko
ATTEST:
__________________________________
City Administrator